Medco Terubuk Development – Construction Management, T&I, Pre-Commissioning

Project

Medco Terubuk Development

Client

PT Timas Suplindo

Location

South Natuna Sea, Indonesia

Project Period

Completed: 2024

Located in Block B of the South Natuna Sea, the Terubuk Development lies approximately 45 km northeast of Belida DPP-A in water depths averaging 275 feet. The field development includes two Minimum Facilities Platforms (WHP-L and WHP-M), interconnecting subsea pipelines, and tie-ins to existing facilities at Belida DPP-A.

OCS Scope:

OCS was engaged by PT Timas Suplindo to provide Construction Management, T&I Engineering, and Pre-Commissioning support for the offshore execution. The project scope comprised:

  • Transportation and installation of two new jackets (WHP-L and WHP-M), drill decks, and PLEM structures, including integration of the ZEEPod substructure and topside modules.
  • Installation of three new 14” pipelines: from WHP-L and WHP-M to the PLEM, and from the PLEM to Belida DPP-A. The system was designed with full pigging capability for operational and maintenance requirements.
  • Brownfield modifications on Belida DPP-A to enable reception and control of Terubuk production, including system integration and remote control interfaces.

Project Outcome:

Offshore execution was carried out using DLB01 & T1201 and successfully completed in November 2024. The project was delivered safely and on schedule, demonstrating OCS’s continued commitment to technical excellence and reliable project delivery.