Menu Close
Project-HESS Indonesia Pangkah Engineering And Project Management

HESS Indonesia Pangkah Engineering And Project Management

Project HESS Indonesia Pangkah Engineering And Project Management
Client
Hees Indonesia Pangkah
Location
Indonesia
Period
2010

Provide Engineering and Project Management for the following work scope (site location Ujung Pangkah, offshore Gresik) :

  • Detail engineering for three Flowlines (approximately 5.5 km long each) – 16” Gas line, 12” Liquid Line and 6” Gas Lift line. From WHP-A (existing) to new WHP-B.
  • Management of pipeline coating for FBE, Neoprene and concrete weight coat.
  • Construction Engineering for the Transportation and Installation of the three Flowlines and WHP-B platform.
  • Transportation and Installation of three Flowlines (including post trenching burial, pigging and hydrotesting, dewatering, drying and nitrogen packing).
  • Transportation of WHP-B platform comprising one 370mT, eight-legged jacket, three section piles and 1500mT Topside.
  • Installation of WHP-B platform comprising one 370mT, eight-legged jacket, three section piles and 1500mT Topside.