Menu Close
Project-Conoco Phillips North Belut Subsea Cable Installation And Project Management

Project-ConocoPhillips North Belut Bridge Engineering And Project Management

Project ConocoPhillips North Belut Bridge Engineering And Project Management
Client
PT TIMAS SUPLINDO
Location
Indonesia
Period
2012

OCS provided the installation management, engineering and planning; including vessel selection, chartering and offshore execution for Conocophillips North Belut CPP Connecting Bridge Installation (site location North Belut Field, Natuna Sea).

  • Detailed installation engineering for installation of the CPP Connecting Bridge between the North Belut CPP and WHP-D platforms.
  • Interfacing with Client and its Subcontractors PTMI, PTTI, Saipem and Sarku maintaining a strict installation window.
  • Construction Engineering for the Transportation and Installation of the Bridge.
  • Transportation of the Bridge from its fabrication yard in Batam to site in Natuna.
  • Installation of the Bridge between the existing facilities.
  • Complete offshore execution was done without incident and ahead of schedule ensuring a positive outcome for all parties.